Building Information Modelling for Construction Delay Management

Description

The Kingdom of Saudi Arabia (KSA) is not an exception in relying on the growth of its construction industry to support rapid population growth. However, its need for infrastructure development is constrained by low productivity levels and cost overruns caused by factors such as delays to project completion. Delays in delivering a construction project are a global issue and while theories such as Optimism Bias have been used to explain such delays, in KSA, client-related causes of delays are also significant. The objective of this paper is to develop a framework-based approach to explore how the country’s construction industry can manage and reduce delays in construction projects through building information modelling (BIM) in order to mitigate the cost consequences of such delays.  It comprehensively and systematically reviewed the global literature on the subject and identified gaps, critical delay factors and the specific benefits that BIM can deliver for the delay management.  A case study comprising of nine hospital projects that have experienced delay and cost overruns was also carried out. Five critical delay factors related to the clients were identified as candidates that can be mitigated through BIM’s benefits. These factors are: Ineffective planning and scheduling of the project; changes during construction by the client; delay in progress payment; slowness in decision making by the client; and poor communication between clients and other stakeholders. In addition, data from the case study projects strongly suggest that optimism bias is present in many of the hospital projects. Further validation via key stakeholder interviews and documentations are planned.

Files

10007656.pdf

Files (331.6 kB)

Name Size Download all
md5:e041ab17f3b4d703524194be37338e97
331.6 kB Preview Download

Additional details

References

  • Deloitte. Deloitte GCC Powers of Construction 2014 Construction Sector Overview; 2014.
  • Ventures Middle East LLC. The Saudi Construction Industry. Abu Dhabi; 2011.
  • Alrashed I, Alrashed A, Taj SA, Phillips M, Kantamaneni K. Risk Assessments for Construction projects in Saudi Arabia. Res J Manag Sci Res J Manag Sci. 2014;3(7):2319-1171.
  • Husein AT. Construction and Projects in Saudi Arabia: Overview Practical Law: Multi-Jurisdictional Guide 2013/2014 Construction and Projects: Association of Corporate Counsel.; 2014.
  • Assaf S A., Al-Hejji S. Causes of delay in large construction projects. Int J Proj Manag. 2006; 24:349-357.
  • AlKharashi A, Skitmore M. Causes of delays in Saudi Arabian public-sector construction projects. Constr Manag Econ. 2009;27(1):3-23.
  • Falqi II. Delays in Project Completion : A comparative study of construction delay factors in Saudi Arabia and the United Kingdom. 2004;(September).
  • Al-Khalil MI, Al-Ghafly M a. Delay in public utility projects in Saudi Arabia. Int J Proj Manag. 1999;17(2):101-106.
  • Zain Al-abidien HM. About the effect of delay penalty on the construction of projects and modification proposal. In: Proceedings of the First Engineering Conference. King Abdulaziz University, Jeddah.; 1983:14-19. [10] Kim H, Soibelman L, Grobler F. Factor selection for delay analysis using Knowledge Discovery in Databases. Autom Constr. 2008;17(5):550-560. [11] Fischer M, John K. The Scope and Role of Information Technology in Construction. CIFE Tech Rep. 2004;(156):1-17. [12] Eastman C, Teicholz P, Sacks R, Liston K. BIM Handbook A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers, and Contractors. John Wiley & Sons, Inc.; 2011. [13] Grilo A, Jardim-Goncalves R. Value proposition on interoperability of BIM and collaborative working environments. Autom Constr. 2010;19(5):522-530. DOI: 10.1016/j.autcon. 2009.11.003. [14] Babič NC, Podbreznik P, Rebolj D. Integrating resource production and construction using BIM. Autom Constr. 2010;19(5):539-543. [15] Azhar S, Hein M, Sketo B. Building Information Modeling (BIM): Benefits, Risks and Challenges. Build Sci. 2008; 18:11. [16] Latham M. Constucting the Team: Joint Review of Procurement and Contractual Arrangements in the United Kingdom Construction Industry. Vol 53.; 1994. [17] Egan SJ. Rethinking construction. Struct Eng. 1998;80(14):2. doi: Construction Task Force. UK Government. [18] Cabinet Office H. Government Construction Strategy, UK Government Report. Vol 96. London; 2011. [19] Sambasivan M, Soon YW. Causes and effects of delays in Malaysian construction industry. Int J Proj Manag. 2007;25(5):517-526. [20] Aibinu, A. A., Jagboro G.O. The effects of construction delays on project delivery in Nigerian construction industry. Int J Proj Manag. 2002;20(8):593-599. [21] Al-Momani AH. Construction delay: a quantitative analysis. Int J Proj Manag. 2000;18(1):51-59. doi:10.1016/S0263-7863(98)00060-X. [22] Odeh A. M, Battaineh HT. Causes of construction delay: Traditional contracts. Int J Proj Manag. 2001;20(June 2000):67-73. [23] Mansfield NR, Ugwu OO, Doran T. Causes of delay and cost overruns in Nigerian construction projects. Int J Proj Manag. 1994;12(4):254-260. [24] Alnuaimi AS, Mohsin M a Al. Causes of Delay in Completion of Construction Projects in Oman. Int Conf Innov Eng Technol. 2013; 99231200:267-270. [25] Macdonald M. Review of Large Public Procurement in the UK. HM Treas. 2002;44(April):1-83. [26] Flyvbjerg B. Procedures for Dealing with Optimism Bias in Transport Planning. Br Dep Transp. 2004;(June):61. [27] Buttonwood. Forecasting a global recession. The Economist. http://www.economist.com/blogs/buttonwood/2015/09/economics. Published 2015. Accessed May 20, 2017. [28] Eastman C, Teicholz P., Sacks R, Liston K. BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors. John Wiley Sons. 2008. [29] Sinclair D. BIM Overlay to the RIBA Outline Plan of Work. R Inst Br Archit. 2012;(Abril):20. [30] Aouad G, Lee A, Wu S. Constructing the Future: nD Modelling. Taylor and Francis, London and New York; 2007. [31] Wu S, Wood G, Ginige K, Jong SW. A technical review of BIMBIM based cost estimating in UK quantity surveying practice, standards and tools. J Inf Technol Constr. 2014;19(November):535-563. [32] Ashworth A. Cost Studies of Buildings. Harlow: Prentice Hall; 2010. [33] Zou Y, Lee S-H. The impacts of change management practices on project change cost performance. Constr Manag Econ. 2008;26(4):387-393. [34] Holness G V. Future direction of the design and construction industry Building inform. ASHRAE J. 2006;48(8):38-46. [35] Newton K, Chileshe N. Awareness, Usage and Benefits of Building Information Modelling (BIM) Adoption – the Case of the South Australian Construction Organisations. Procs 28th Annual ARCOM Conf. 2012:3-12. [36] Aibinu A, Venkatesh S. Status of BIM adoption and the BIMBIM experience of cost consultants in Australia. Am Soc Civ Eng. 2013;140(3):1-10. [37] Farnsworth CB, Beveridgea S, Miller KR, Christofferson JP. application, advantages, and methods associated with using BIM in commercial associated construction. Int J Constr Educ Res. 2014;10(1080):1557-8771. [38] Khosrowshahi F, Arayici Y. Roadmap for implementation of BIM in the UK construction industry. Eng Constr Archit Manag. 2012;19(6):610-635. [39] Barlish K, Sullivan K. Automation in Construction How to measure the benefits of BIM — A case study approach. 2012; 24:149-159. [40] Lorch R. BIM and the public interest. Build Res Inf. 2012;40(6):643_644. [41] Nassar K. The Effect of Building Information Modeling on the Accuracy of Estimates. In: The Sixth Annual AUC Research Conference. Cairo. The American University; 2010. [42] Doloi H, Sawhney A, Iyer KC. Structural equation model for investigating factors affecting delay in Indian construction projects. Constr Manag Econ. 2012;30(10):869-884. [43] Gledson BJ, Greenwood D. The implementation and use of 4D BIM and virtual construction. Proc 30th Annu Assoc Res Constr Manag Conf ARCOM 2014. 2014;(September 2014):673-682. [44] Matipa WM, Cunningham P, Naik B. Assessing the impact of new rules of cost planning on building information model (BIM) schema pertinent to quantity surveying practice. 26th Annu ARCOM Conf. 2010;(September):625-632. [45] Goucher D, Thurairajah N. Usability and impact of BIM on early estimation practices: Cost consultant's perspective. IrbnetDe. 2012:555-570. [46] Sackey E. A Sociotechnical Systems Analysis of Building Information Modelling (STSaBIM) Implementation in Construction Organisations. 2014. [47] Tessema YA. BIM for Improved Building Design Communication Between Architects and Clients in the Schematic Design Phase. 2008. [48] Arayici Y, Coates S, Koskela L, Kagioglou M, Usher C, O'Reilly K. BIM implementation for an architectural practice. 2009. [49] Azhar S, Behringer A. A BIM-based Approach for Communicating and Implementing a Construction Site Safety Plan. 49th ASC Annu Int Conf Proc. 2013. [50] Chelson DE. The effects of building information modeling on construction site productivity. 2010. [51] Hungu CF. Utilization of BIM from Early Design Stage to facilitate Efficient FM Operations. Dep Civ Environ Eng. 2013; Master of. [52] Smith P. BIM & the 5D Project Cost Manager. Procedia - Soc Behav Sci. 2014; 119:475-484. [53] Albogamy A, Scott D, Dawood N, Bekr G. Addressing Crucial Risk Factors in the Middle East Construction Industries: A comparative Study of Saudi Arabia and Jordan. 2013:118-128. [54] Luu VT, Kim S-Y, Tuan N Van, Ogunlana SO. Quantifying schedule risk in construction projects using Bayesian belief networks. Int J Proj Manag. 2009;27(1):39-50. [55] Alaghbari W, Kadir MR a., Salim A, Ernawati. The significant factors causing delay of building construction projects in Malaysia. Eng Constr Archit Manag. 2007;14(2):192-206. [56] Bew M, Underwood J. Delivering BIM to the UK Market. Handb Res Build Inf Model Constr Informatics Concepts Technol. 2010:30-64. [57] Kassem M, Iqbal N, Kelly G, Lockley S, Dawood N. Building Information Modelling: Protocols for Collaborative Design Processes. ITcon. 2014;19(July):126-149. [58] Li J, Wang Y, Wang X, et al. Benefits of building information modelling in the project lifecycle: Construction projects in Asia. Int J Adv Robot Syst. 2014;11(1). [59] Bolpagni M. The Implementation of BIM within the Public Procurement A Model-Based Approach for the Construction Industry.; 2013. [60] Whyte J. Building Information Modelling in 2012: Research Challenges, Contributions, Opportunities. Des Innov Res Cent Work Pap. 2012;(5):1-22. [61] McGraw-Hill Construction. The Business Value of BIM for Construction in Major Global Markets: How Contractors around the World Are Driving Innovation with Building Information Modeling. (Bernstein HM, ed.). Breadford: McGraw Hill Construction; 2014. [62] Zhang S, Teizer J, Lee JK, Eastman CM, Venugopal M. Building Information Modeling (BIM) and Safety: Automatic Safety Checking of Construction Models and Schedules. Autom Constr. 2013; 29:183-195. [63] Hunt CA. The Benefits of Using Building Information Modeling in Structural Engineering. 2013:31-37. [64] Kaner I, Sacks R, Kassian W, Quitt T. Case studies of BIM adoption for precast concrete design by mid-sized structural engineering firms. Electron J Inf Technol Constr. 2008;13(September 2007):303-323. [65] Tsai TC, Yang ML. Risk assessment of design-bid-build and design-build building projects. J Oper Res Soc Japan. 2010;53(1):20-39. [66] Jackson S. Project Cost Overruns and Risk Management. Assoc Res Constr Manag 18th Annu ARCOM Conf Newcastle, Northumbria Univ UK. 2002:2-4. [67] Hossen MM, Kang S, Kim J. Construction schedule delay risk assessment by using combined AHP-RII methodology for an international NPP project. Nucl Eng Technol. 2015;47(3):362-379. [68] Callahan MT. Construction Change Order Claims. New York: Aspen; 2005. [69] Duke WM, Johnson PW, Leopard TA. Building Information Modeling: How It Can Benefit a Modern Construction Project in a University Setting. 2013. [70] Stasis A, Whyte J, Stephens E, Dentten R. Building Information Modelling and Management in Infrastructure Programmes: A Scoping Study in Crossrail. Transp Res Board 92nd Annu Meet. 2013:1-10. [71] Love PED, Simpson I, Hill A, Standing C. From justification to evaluation: Building information modeling for asset owners. Autom Constr. 2013; 35:208-216. [72] Zanni M A., Soetanto R, Ruikar K. Facilitating BIM-Based Sustainability Analysis and Communication in Building Design Process. 2013;(August):20-22. [73] Talebi S. Rethinking the project development process through use of BIM. 2nd BIM Int Conf Challenges to Overcome. 2014:1-19. [74] Sweis G, Sweis R, Abu Hammad A., Shboul A. Delays in construction projects: The case of Jordan. Int J Proj Manag. 2008; 26:665-674. [75] Mitra S, Wee Kwan Tan A. Lessons learned from large construction project in Saudi Arabia. Benchmarking An Int J. 2012;19(3):308-324. [76] Ghahramanzadeh M. Managing Risk of Construction Projects A case study of Iran. 2013;(October). [77] Assaf S A., Al-Khalil M, Al-Hazmi M. Causes of Delay in Large Building Construction Projects. J Manag Eng. 1995;11(2):45-50. [78] Dulaimi MF, Nepal MP, Park M. A HIERARCHICAL STRUCTURAL MODEL OF ASSESSING INNOVATION AND PROJECT PERFORMANCE. 2005;23. [79] Asnaashari E, Knight A, Hurst A, Farahani SS. Causes of Construction Delays in Iran: Project Management, Logistics, Technology and Environment. 25th Annu ARCOM Conf 7-9 Sept 2009, Nottingham, UK. 2009;(September):897-906. [80] Ramanathan C, Narayanan SP, Idrus AB, Teknologi U. Construction Delays Causing Risks on Time and Cost - a Critical Review. 2002. [81] Shebob A, Dawood N, Shah RK. Development of a methodology for analysing and quantifying the impact of delay factors affecting construction projects. J Constr Eng Proj Manag. 2012;2(3):17-29. [82] Faridi A, El-Sayegh S. Significant factors causing delay in the UAE construction industry. Constr Manag Econ. 2006;24(11):1167-1176. [83] Olatunji AA. Influences on Construction Project Delivery Time. 2010;(December):1-314. [84] Scherer RJ, Schapke S-E. A distributed multi-model-based Management Information System for simulation and decision-making on construction projects. Adv Eng Informatics. 2011;25(4):582-599. [85] Dave B. Developing a construction management system based on lean construction and building information modelling. 2013. [86] BIS. Infrastructure Supply Chains: Barriers and Opportunities. Department for Business, Innovation and Skills. London; 2011. [87] Noordeen S, Karthikeyan K, Parveen M a N. Evaluation of Design Construction Interface in Construction Industry. Int J Eng Res Technol. 2013;2(4):388-397. [88] Saini M. A framework for transferring and sharing tacit knowledge in construction supply chains within lean and agile processes. 2015. [89] Haron AT. Organisational Readiness to Implement Building Information Modelling: A Framework for Design Consultants in Malaysia. 2013;(April). [90] Chien KF, Wu ZH, Huang SC. Identifying and assessing critical risk factors for BIM projects: Empirical study. Autom Constr. 2014; 45:1-15. [91] Clevenger C, Glick S, del Puerto CL. Interoperable Learning Leveraging Building Information Modeling (BIM) in Construction Education. Int J Constr Educ Res. 2012;8(February 2015):101-118. [92] Kuehmeier JC. BUILDING INFORMATION MODELING AND ITS IMPACT ON DESIGN AND CONSTRUCTION FIRMS. A Thesis Present To Grad Sch Univ Florida Partial Fulfillment Requir Degree Master Sci Build Constr Univ Florida. 2008:1-56. [93] Wang Y, Wang X, Wang J. Engagement of facilities management in design stage through BIM: framework and a case study. Adv Civ …. 2013;2013(30836). [94] Masood R, Kharal MKN, Nasir, A. R. Is BIM Adoption Advantageous for Construction Industry of Pakistan? Procedia Eng. 2014; 77:229-238. [95] Succar B, Kassem, M., Succar B. and D. N., Kassem, M., Iqbal, N., Kelly, G., Lockley, S., Dawood N., et al. The Five Components of BIM Performance Measurement. Build Des. 2014;19(September):287-300. [96] Rohkohl J. MEP Engineering Solutions for Building Systems Design and Document First-Rate Building Systems Keep design data more accurate and coordinated, minimize errors, and enhance collaboration with Autodesk software for MEP projects. [97] Leite F, Akcamete A, Akinci B, Atasoy G, Kiziltas S. Analysis of modeling effort and impact of different levels of detail in building information models. Autom Constr. 2011;20(5):601-609. [98] Arayici Y, Egbu C, Coates P. Building information modelling (BIM) implementation and remote construction projects: Issues, challenges, and critiques. Electron J Inf Technol Constr. 2012;17(May):75-92. [99] Aditi D. Delay Analysis in Construction Contracts. Int J Emerg Technol Adv Eng. 2014;4(5):784-788.