There is a newer version of the record available.

Published September 30, 2024 | Version 1.0.0
Dataset Open

Monthly Hydropower Generation Dataset for Western Canada

  • 1. ROR icon Pacific Northwest National Laboratory

Description

The presented dataset contains the following simulation-based monthly hydropower generation data for 110 facilities in British Columbia and Alberta, to support Western-US interconnect grid system studies:
1) Monthly hydropower generation estimates
2) Monthly hydropower flexibility metrics (minimum and maximum hourly generation and daily fluctuations)

The hydropower generation estimates are provided with reference to the facility list that contains the corresponding metadata for each facility.

For more details, please refer to Son et al. (2024). Monthly hydropower generation data for Western Canada to support Western-US interconnect power system studies [Manuscript submitted for publication].

Corresponding author(s): Youngjun Son (youngjun.son@pnnl.gov) and Nathalie Voisin (nathalie.voisin@pnnl.gov)

For data reproduction, please see the GitHub repository at https://github.com/GODEEEP/tgw-hydro-canada.

Hydropower Facility List

The file, CAN_hydropower_facilities.csv, provides essential information on 146 hydropower facilities in British Columbia and Alberta, derived from Renewable Energy Power Plants, 1 MW or more, by Energy Source by North American Cooperation on Energy Information (NACEI). Additionally, the facility information has been updated with corresponding National Hydrographic Network (NHN) Work Units, global reservoir and lake database (GRanD: Global Reservoirs and Dams Database and HydroLAKES), diversion intake flow rates based on water license information (hydropower), and so on. Below are the descriptions for each column in the facility metadata:

  • fid: Facility id according to NACEI data. New four-digit id starting with '9' are assigned for facilities with no fid in NACEI data
  • Facility: Name of the facility
  • X: Longitude of the facility's powerhouse
  • Y: Latitude of the facility's powerhouse
  • Province: Province where the facility is located
  • Hydro_MW: Nameplate capacity of the facility
  • NHN_Work_U: Associated NHN Work Units
  • GRanD_ID: Associated reservoir id from the GRanD dataset
  • HydroLAKES_ID: Associated lake id from the HydroLAKES dataset
  • GINDEX: Grid id from the mosartwmpy Canada model
  • GINDEX_CONUS: Grid id from the mosartwmpy CONUS model, used for facilities in the Columbia River Basin
  • Basin_Note: Indicator for facilities located in the Columbia River Basin or outside of the TGW meteorological forcing domain
  • WECC_ADS_2032: Indicator for facilities without the WECC ADS 2032 reference hydropower generation data
  • Intake_Flow_Rate: Diversion intake flow rates based on hydropower water license information
  • Type: Type of facility
  • Water_License: Link to the source of water license information

Among the 146 hydropower facilities listed, only 110 facilities, which are within the TGW meteorological forcings domain and have reference hydropower generation data, are considered for monthly hydropower generation estimates.

Monthly Hydropower Generation Estimates and Flexibility Metrics

Each file contains a monthly timeseries dataset (rows: monthly timestamps) from 1981 to 2019 for 110 facilities (columns: Facility listed in CAN_hydropower_facilities.csv).

  1. CAN_hydropower_monthly_generation_MWh.csv: monthly total hydropower generation in MWh
  2. CAN_hydropower_monthly_p_min_MW.csv: monthly flexibility metric of minimum generation capacity in MW
  3. CAN_hydropower_monthly_p_max_MW.csv: monthly flexibility metric of maximum generation capacity in MW
  4. CAN_hydropower_monthly_p_ador_MW.csv: monthly flexibility metric of the daily operation range in MW

Funding Acknowledgements

This work was supported by the Grid Operations, Decarbonization, Environmental and Energy Equity Platform (GODEEEP) Investment, under the Laboratory Directed Research and Development (LDRD) Program at the Pacific Northwest National Laboratory (PNNL).

The PNNL is a multi-program national laboratory operated by Battelle Memorial Institute for the U.S. Department of Energy (DOE) under Contract No. DE-AC05-76RL01830.

Disclaimer

The presented dataset was prepared as an account of work sponsored by an agency of the U.S. Government. Neither the U.S. Government nor the U.S. Department of Energy, nor the Contractor, nor any or their employees, nor any jurisdiction or organization that has cooperated in the development of these materials, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness or any information, apparatus, product, software, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the U.S. Government or any agency thereof, or Battelle Memorial Institute.

Files

CAN_hydropower_facilities.csv

Files (3.8 MB)

Name Size Download all
md5:e10e06c2bb8ff2de6ffc70d2d511cd62
24.5 kB Preview Download
md5:2b70298de644ef28ec173af931154c00
948.4 kB Preview Download
md5:2dbabccac83f698da89b4adde3cebf99
958.1 kB Preview Download
md5:d7a1aa1c0335ad2bb781350d8fdef5e3
946.7 kB Preview Download
md5:7fedee8ead675be9dab294c42ffd050d
960.3 kB Preview Download

Additional details

Software

Repository URL
https://github.com/GODEEEP/tgw-hydro-canada
Programming language
Python