D1.2.3 Project Management Plan
Authors/Creators
- 1. Universidad Nacional de Educación a Distancia (UNED)
- 2. Análisis-DSC
Description
This deliverable updates the current work plan and the schedule of the ASTEP project, including the latest information in the amendment AMD-884411-22. The Gantt chart, the Pert chart and the Work Breakdown Structure of the project are presented, including the schedule of Tasks and Subtasks, their responsible partner and person, the related deliverables and their dependencies.
The Project Management Plan is a fundamental guide for all the partners within the consortium, as project contributors can find important information for the day-to-day work related with the general structure of the project work plan and important information regarding the data flow and links between the different WPs, Tasks, Subtasks, Deliverables and Milestones.
The report is divided into two parts. The first one focuses on the overall work plan, which is detailed at Task level. The aim of this part is to update and complete the information contained in the Grant Agreement, including the responsible partner and person for each Task, and to analyse the dependencies between Tasks, Deliverables and Milestones. The information is given by tables, an overall Gantt chart and an overall Pert chart.
The second part of the report focuses on the detailed Work Breakdown Structure of the project, including the definition of Subtasks that meet the overall dependencies previously detected. Also, the responsible partner and person for each Subtask are defined, as well as the schedule for the Subtasks and the links between them. The information is presented by means of Tables, Gantt charts for the different Work-Packages and a comprehensive Pert Chart for the whole project.
Therefore, the analysis of dependencies was done at two levels: one considering overall flows (first part of the report) and another one detailing links between Subtasks (second part). The analyses at the beginning of the project led to a schedule slightly different to that programmed in the Grant Agreement, with the aim of extending the time for critical activities like commissioning and decommissioning and enlarging testing activities. At M18, despite the deviations over the first PMP, the project was in the position of starting the second period with some additional time for the testing activities at laboratory without incurring in delays in the testing activities at the end-users sites.
During the execution of the second reporting period (from M18 to M36) some issues in the supply chain and bad weather in one of the demo-sites have caused significant delays. A new timeline has been requested and approved by the EC with the signature of the amendment AMD-884411-22. The dates presented in this new release of the Project Management Plant has been accordingly updated.