GreenCharge Project Deliverable: D2.19 Full-Scale Pilot Implementation for Smart Charge and EV Fleet Management
Authors/Creators
- 1. ATLANTIS IT SLU
- 2. FUNDACIO EURECAT
- 3. MOTIT
- 4. MILLOR ENERGY SOLUTIONS SL
Description
This deliverable presents the implementation of each demonstrator of the Barcelona Pilot. The components used were previously described on the deliverable D2.18 Pilot Component Preparation for Full-scale Pilot (Barcelona).
All the developments and adaptations needed for the integrated prototypes for the first iteration have been done for the 3 demonstrators, although the hardware installation has been delayed for some of the demonstrators.
The table below shows the status of each demonstrator per 9 April 2021, indicating when fully completed or work is still on progress.
|
Demonstrator |
Task | Comments | Status |
|---|---|---|---|
|
MOTIT |
Software development/adaptation |
Communication issues with battery management system caused delays on implementation |
Fully completed |
|
MOTIT |
Hardware installation |
|
Fully completed |
|
MOTIT |
Configuration |
|
Fully completed |
|
MOTIT |
Full tests |
|
Fully completed |
|
MOTIT |
Start data acquisition |
Automatic data collection: on going |
Fully completed |
| Eurecat | Software development/adaptation |
Hardware installation completed in Cerdanyola premises. Additional premises are planned for 2nd iteration |
Fully completed |
| Eurecat | Hardware installation |
|
Fully completed |
| Eurecat | Configuration |
|
Fully completed |
| Eurecat | Full tests |
|
Fully completed |
| Eurecat | Start data acquisition |
Static baseline: on going Automatic data collection: on going |
Fully completed |
|
e-bike sharing |
Software development/adaptation |
|
Fully completed |
|
e-bike sharing |
Hardware installation |
Bike batteries, charge points, PV panel and stationary battery are all installed. |
Fully completed |
|
e-bike sharing |
Configuration |
|
Fully completed |
|
e-bike sharing |
Full tests |
|
Fully completed |
|
e-bike sharing |
Start data acquisition |
Pending service reopening due to COVID19. |
On progress |