OPTIMAL ASSIGNMENT OF PRECAST COMPONENTS TO MINIMIZE CURING COST

  • 1. ROR icon Louisiana State University

Description

Efficient production of precast concrete components is essential for transportation infrastructure projects, where strict schedule compliance and effective cost management directly influence project feasibility and contractor performance. This study develops a method to minimize the curing cost that effectively maximizes pallet capacity utilization during the curing process of precast concrete manufacturing. The model incorporates practical operational constraints, including demand satisfaction, mold availability, pallet dimensions, spacing requirements between components, weight limits, and labor-related loading and unloading costs, while allowing multiple component geometries to be arranged within a single pallet configuration. By dynamically adjusting pallet layouts across successive production cycles, the framework captures demand variability, resource limitations, and operational uncertainties inherent in real precast plants. The proposed approach improves pallet space usage, reduces unnecessary pallet cycles, lowers curing energy consumption, and minimizes labor expenses without compromising curing quality or structural performance. Validation using real-world industry data demonstrates measurable reductions in curing-related costs and significant improvements in overall resource utilization and production efficiency. Beyond the curing stage, the optimized pallet layout structures provide a systematic spatial foundation that can be extended to enhance mold placement during casting and improve storage layout planning after demolding. As a result, the model supports integrated decision-making across curing, mold utilization, and storage operations. The proposed framework offers a scalable, data-driven decision-support tool that strengthens precast production planning and enhances the reliability and efficiency of transportation infrastructure delivery systems. 

Files

OPTIMAL ASSIGNMENT OF PRECAST COMPONENTS TO MINIMIZE CURING COST.pdf

Files (531.0 kB)

Additional details

Related works

Is described by
Project deliverable: https://trans-ipic.illinois.edu/research (URL)

Funding

United States Department of Transportation
University Transportation Center program 69A3552348333

References

  • Benjaoran, V., Dawood, N. and Hobbs, B., 2005. Flowshop scheduling model for bespoke precast concrete production planning. Construction Management and Economics, 23(1), pp. 93-105.
  • Chan, W.T. and Hu, H., 2002. Production scheduling for precast plants using a flow shop sequencing model. Journal of computing in civil engineering, 16(3), pp. 165-174.
  • Hong, W.K., Lee, G., Lee, S. and Kim, S., 2014. Algorithms for in-situ production layout of composite precast concrete members. Automation in Construction, 41, pp. 50-59.
  • Ko, C.H. and Wang, S.F., 2011. Precast production scheduling using multi-objective genetic algorithms. Expert Systems with Applications, 38(7), pp. 8293-8302.
  • Liang, J., Cao, Z., Zu, Q., Huang, H. and Guo, S., 2024. Production sequencing and layout optimization of precast concrete components under mold resource constraints. Buildings, 14(10), p.3173.
  • Mazumder, A. and Sarker, B. R., 2025. Optimal vendor-manufacturer cooperative policy for perishable precast materials under stochastic demand and lead-time uncertainty. http://dx.doi.org/10.2139/ssrn.5439845
  • Mazumder, A. and Sarker, B. R., 2026a. Determining Optimal Variable Order Quantities of Raw Materials for Precast Concrete Production Considering Demand Variability and Uncertain Material Prices. Submitted to Asia Pacific Journal of Operational Research. 1st submission: September 8, 2025; 1st Revision: February 12, 2026. (APJOR: M250908).
  • Mazumder, A. and Sarker, B. R., 2026b. Optimal Pallet and Components Assignment Configuration to Minimize Curing Cost in Precast Manufacturing. Submitted to Annals of Operation Research. 1st submission: January 27, 2026 (ANOR-D-26-00288).
  • Prata, B., Pitombeira-Neto, A.R. and de Moraes Sales, C.J., 2015. An integer linear programming model for the multiperiod production planning of precast concrete beams. Journal of Construction Engineering and Management, 141(10), p.04015029.
  • Sarker, B. R. and Mazumder, A., 2025, Developing a Cost-Effective, Reliable and Sustainable PC Supply System Under Price Volatility and Uncertain Materials Supply. https://rosap.ntl.bts.gov/view/dot/89200
  • Soni, A., Das, B., Brand, M., and Bivins, A., 2026. Aerobic Treatment Units for Widespread On-Site Wastewater Treatment in Coastal Louisiana: Pollution, Policy, and Market-Based Solutions. Preprints. https://doi.org/10.20944/preprints202602.1969.v1
  • Wang, D., Liu, G., Li, K., Wang, T., Shrestha, A., Martek, I. and Tao, X., 2018. Layout optimization model for the production planning of precast concrete building components. Sustainability, 10(6), p.1807.
  • Xue, H., Zhang, S., Su, Y. and Wu, Z., 2017. Factors affecting the capital cost of prefabrication—A case study of China. Sustainability, 9(9), p.1512.
  • Yang, Z., Ma, Z. and Wu, S., 2016. Optimized flowshop scheduling of multiple production lines for precast production. Automation in Construction, 72, pp. 321-329.