D1.1 Quality Assurance Plan

  • 1. ROR icon Tecnalia

Description

The deliverable is structured in several chapters explaining the following key aspects related to the quality assurance in the project:


• Detailed work plan for each WP
• Procedure for deliverables review
• Templates and formats for different documents, meetings, etc.
• Internal communication channels
• Innovation management
• Project Management Plan


Note: the PUSH2HEAT proposal was submitted with four demo sites but one of them (the pilot plant to be implemented at CAPSA) failed during the GA preparation phase. CAPSA is not officially a beneficiary of the PUSH2HEAT project and the consortium is looking for a demo site that will substitute it. Once the alternative demo site is confirmed the responsibilities that should have been assumed by CAPSA will be transferred to the new partner. However, it has not been possible to confirm the alternative demo site yet, so for the sake of clarity ‘CAPSA’ and ‘demo site in Spain’ are used to refer to this demo site.

Files

PUSH2HEAT_D1.1.Quality-Assurance-Plan_v0.3_FINAL.pdf

Files (967.6 kB)