Magnet contructed and tested
Creators
Description
This report presents Milestone MS56 of I.FAST Work Package 11, dedicated sustainable concepts and innovative technologies.
Within Task 11.3, the realization of PM-based combined function magnet with dipole and quadrupole fields, aimed towards the magnets used in the Diamond-II lattice have been successfully designed and manufactured.
Dimensional checks and the related activities confirm overall compliance with project specifications. Although a few deviations from nominal tolerances were identified, they are minor, non-critical, and manageable in the final magnet assembly.
The completion of this milestone provides validated components for the next phase of the WP11.3, enabling the measurement of this new Permanent Magnet Quadrupoles & Combined Function Magnets for Ultra Low-Emittance Rings at Daresbury Laboratory (Deliverable 11.3).