Published 2024 | Version v1

IMPLEMENTATION OF MAGNETISM IN MATERIAL HANDLING SYSTEM

Description

The project focuses on the design and production of a ground floor crane fitted with a load locking unit at any
level as a special feature, to address the problem of failure due to a fixed load. The mobile crane is designed to carry a maximum
load of about 5 kg, and a counterweight of 50 kg. The materials used are; sheet metal, profile bars, bolts, nuts, metal rolls etc.
Processing procedures include cutting, filling, welding and assembling. For permanent contact, the arc welding process was
used. As mentioned earlier, a ground floor crane gains its value in the transport of heavy machine parts inside and outside the
workspace. It can also be used to load and unload machine parts onto trucks.
 