USING CRITICAL PATH METHODS IN THE MANAGEMENT OF RETROFITTING PROJECTS. CASE STUDY

  • 1. University of Oradea

Description

Purpose – The paper proposes the application of the critical path method in the management of a retrofitting project. The tool used is the Microsoft Project program.

Methodology/approach - It was considered the concrete case of a retrofitting project of a CNC machine tool, a project carried out within a company from Oradea. Thus, the activities to be carried out within the project were identified. Each activity was associated with duration. The necessary resources for carrying out each activity and the costs with them were established. The technological dependencies between the activities were established. All this information was entered into the Microsoft Project program.

Findings – The use of the Microsoft Project program allowed highlighting the critical path within the project. In order to reduce the duration of the project execution, the durations of the activities within the critical path (critical activities) must be reduced.

Research limitations/implications – The paper proposes a retrofitting project management solution.

Practical implications This approach supports the companies whose object of activity is this type of project. The method is a tool to streamline project management.

Originality/value – The paper proposes the use of critical path methods in retrofitting projects, through the Microsoft Project program.