This dataset summarizes the amount of energy that should be curtailed in order to obtain the desired reduction at the monitored cross-border line.

This amount is not linear and depending on the congestion size, the curtailment cost might be really expensive. This data summarizes the KPI results of analysing the real curtailment requirements when facing different congestions. Two scenarios are considered:

  • In the line between substations GKORIN and G1ARGOS
  • In the line between substations G2PATR31 and GSIMOP31

For each unit of power reduction needed (x-axis) the corresponding curtailment required is presented (y-axis)

Files

Files (28.1 kB)

Name Size Download all
md5:0bf008f2805b229e4b76055d2e9ba53f
28.1 kB Download

Additional details

Funding

European Commission
CROSSBOW - CROSS BOrder management of variable renewable energies and storage units enabling a transnational Wholesale market 773430