Identifying and Hierarchizing the factor of Delay Factors with Interpretive Structure Modelling a case in Indian Thermal Power Plant
Authors/Creators
- 1. Dept. Humanities and Management, Manipal Institute of Technology, Manipal Academy of Higher Education, India
- 2. Tata Consulting Engineers Limited, Bengaluru, India
- 3. Humanities and Management, Manipal Institute of Technology, Manipal Academy of Higher Education, India
Contributors
Researcher:
- 1. Dept. Humanities and Management, Manipal Institute of Technology, Manipal Academy of Higher Education, India
Description
Project(s) to succeed four key factors are important; they are manpower, finance, material and time. The finance is an essential component than the rest and the key role played by the finance department is critical for project completion success. The project manager ensures that the project completes within timeline, as every delay incurs cost-overrun. The consulting firm is responsible for the project that probes the causes for time and money delay factors. This study sheds light on the delay factors that causes cost escalation on the project managers to have to deal with during the project. Cost escalation of the project is a significant cause of concern to the client as the requirement to make financial arrangement for the project is very important. The objective is to list and rank the significant causes of delay that occurs during the construction of the project based on prior work done by other researchers and experts in the field from the company. The ranking the delays is done by three methods-Relative Importance Index (RII), Importance Index (IMP.I) and Total Risk Score (TRS). Using the three approaches the delay causes are ranked based on the responses from experienced projects managers via survey questionnaire in projects site. The cost of escalation by di-graph shows nine delay causes were considered as critical causes and the nine variables were used in developing and Interpretive Structural Model (ISM) showing the interrelationship among the delay causes. If was found that the cost of the project increases with a delay in completion time, based on the ranking of the delay causes. Based on the results obtained recommendations are given to mitigating these delays.
Files
Identifying and Hierarchizing the factor of Delay Factors with.pdf
Additional details
References
- Alnuaimi, A. S., & Mohsin, M. (2013, December). Causes of delay in completion of construction projects in Oman. In International Conference on Innovations in Engineering and Technology (pp. 267-270).
- Kometa, S. T., Olomolaiye, P. O., & Harris, F. C. (1994). Attributes of UK construction clients influencing project consultants' performance. Construction Management and Economics, 12(5), 433-443.
- Megha, D., & Rajiv, B. (2013). A methodology for ranking of causes of delay for residential construction projects in Indian context. International Journal of Emerging Technology and Advanced Engineering, 3(3), 396-404.
- Ravisankar, K. L., AnandaKumar, S.& Krishnamoorthy, V. (2014). Study on the Quantification of Delay Factors in Construction Industry. International Journal of Emerging Technology and Advanced Engineering.4(1), 105-113
- Shebob, A., Dawood, N., & Shah, R. K. (2012). Development of a methodology for analysing and quantifying the impact of delay factors affecting construction projects. Journal of Construction Engineering and Project Management,2(3), 17-29.
- Singh, R. K. (2011). Developing the framework for coordination in the supply chain of SMEs. Business Process Management Journal, 17(4), 619-638.
- Sweis, G., Sweis, R., Hammad, A. A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6), 665- 674.
- Tumi, S. Al. H., Omran, A. & Pakir, A. H. K.(2009). CAUSES OF DELAY IN CONSTRUCTION INDUSTRY IN LIBYA. The International Conference on Economics and Administration, Faculty of Administration and Business, University of Bucharest, Romania ICEA – FAA Bucharest, 14-15th November 2009, p. 265 – 272.
- Jayasudha, K., Vidivelli, B. & Surjith, E. R. G.(2014), Risk Assessment and Management in Construction Projects. International Journal of Scientific & Engineering Research, 5(8), 387-396.
- Warfield, J. N. (1974). Developing interconnection matrices in structural modeling. IEEE Transactions on Systems, Man, and Cybernetics, 4(1), 81-87.