James Webb Space Telescope (JWST) Optical Telescope Element (OTE) Pathfinder status and plans

Description

A JWST OTE Pathfinder telescope that includes two spare primary mirror segments, a spare secondary mirror, and a large composite structure with a deployed secondary support structure is in the assembly stage and will be fully completed this year. This Pathfinder will check out key steps in the ambient mirror integration process and also be used at the Johnson Space Center (JSC) to check out the optical Ground Support Equipment (GSE) and associated procedures that will be used to test the full JWST telescope and instruments at JSC. This paper will summarize the Pathfinder integration and testing flow, the critical Ground Support Equipment it will test and the key tests planned with the Pathfinder.