Computing Cost and Time Contingency for Box Culverts Construction Projects using Integrated Risk Management Technique

  • 1. Ph.D. Student of Irrigation and Hydraulics Engineering Department, Faculty of Engineering – Ain Shams University, Cairo, Egypt.
  • 2. Professor of Irrigation and Hydraulics Engineering Department, Faculty of Engineering – Ain Shams University, Cairo, Egypt.
  • 3. Professor of Hydraulics and Water Resources, Irrigation and Hydraulics Department, Faculty of Engineering – Ain Shams University, Cairo, Egypt, Vice –President of Student Affairs at 6th of October University, Egypt.
  • 4. Associated Professor of Irrigation and Hydraulics Department, Faculty of Engineering – Ain Shams University, Cairo, Egypt.

Description

Abstract: Construction and rehabilitation of water control structures in Egypt considered as an important project, as it influences the usage of water resources in Egypt which become limited resources due to water scarcity existed in the last decades. Also these projects helps in the optimization of water resources, Moreover it helps in the growth of agricultural and industrial sector. Project Risk Management (RMP) is considered as a vital and important tool in decision making, thus RMP used as a planning management system to detect risks affecting project deliverables; such as cost and time target. This research shows how to optimize the deliverables for construction of box culverts in Egypt, through a well-defined risk management framework and real case study for a certain project executed in the last decade. Finally, this study shows how to calculate cost and time contingency for these projects through an integrated risk management technique. Finally this study shows hazard risk identification and assessment for these type of projects. The conclusion of this study show that the cost contingency needed to resolve different risk factors arise in the shown case study is to increase the estimated budget with average value 11.50 percent on the total estimated budget, as well as the time contingency is found with average value 16.00 percent to be added over the total original baseline schedule of the construction project.

Notes

Published By: Blue Eyes Intelligence Engineering and Sciences Publication (BEIESP) © Copyright: All rights reserved.

Files

E35360611522.pdf

Files (865.1 kB)

Name Size Download all
md5:64ac597da40e590f46b08c06a947c027
865.1 kB Preview Download

Additional details

Related works

Cites
Journal article: 2249-8958 (ISSN)

References

  • Ibrahim Abdel Rashid (2009), "Risk and Risk Management definitions" Lectures in construction management, Faculty of Engineering, Cairo University, 2009, Cairo, Egypt.
  • M. A. Ashour , S. T. El Attar , Y. M. Rafaat and M. N. Mohamed (2009) , "Water resources management in Egypt" , Journal of Engineering Sciences, Assiut University, Vol. 37, No. 2, pp. 26979.
  • Nael Zabaal (2007), "Risk management of pipeline infrastructure projects in Egypt". Thesis (M.Sc.) Faculty of Engineering, Cairo University, Cairo, Egypt.
  • Omar Mohamed, Mohamed Nour, Iman Elazizy, Mona A. Hagras (2020), "A suggested module for risk framework of water Control Construction Projects using qualitative and quantitative techniques" International Journal of Engineering and Advanced Technology (IJEAT), ISSN: 2249 – 8958, Volume-9 Issue-3.
  • Pooworakulchai, C. (2018), "Applied risk management in construction industry: A Review ". (Research gate) International Journal of engineering technologies and management research, Vol.5 (Iss.3), ISSN: 2454-1907.
  • Project Management Institute (PMI). A Guide to the Project management Body of Knowledge (PMBOK Guide), 2017 6thEdition, ANSI/PMI 99-001-2017, Newton Square, Pennsylvania.
  • Rafiq M. Choudhry, Sana Rafiq, Anwar Ahmed, Tauqir Ahmed (2018), "Estimating Probabilistic Cost and Time Contingency for Residential Building Projects". (Research gate) Proceedings of the 3rd International Conference on Civil, Structural and Transportation Engineering (ICCSTE'18), Niagara Falls, Canada – June 10 – 12, 2018, Paper No. 134, DOI: 10.11159/iccste18.134.
  • Saeed, S. "Cost and Time Risk Management in Construction Projects". (Research gate) Tikrit Journal of Engineering Sciences, ISSN: 1813-162X (Print); 2312-7589 (Online), Kirkuk University, Iraq.
  • Tarek Alkhrdaji and Antonio Nanni (2001), "Design, Construction, and Field-Testing of an RC Box Culvert Bridge Reinforced with GFRP Bars ". (Research gate) Center for Infrastructure Engineering Studies (CIES), University of Missouri-Rolla, USA.
  • Thomas L.Saaty (2013), "Decision Making with the Analytic ". Network Process International Series in Operations Research & Management Science Volume 195, Stanford University, Stanford, CA, USA.
  • W. Gunidy, "Egypt is the gift of Nile ", National water research center, Ministry of Water resources and irrigation, 2015, Cairo, Egypt.

Subjects

ISSN: 2249-8958 (Online)
https://portal.issn.org/resource/ISSN/2249-8958#
Retrieval Number: 100.1/ijeat.E35360611522
https://www.ijeat.org/portfolio-item/E35360611522/