D5.2 - Use case implementation plan

Michał Kłosiński

Project member(s)
Enrico Abate-Daga; Davide Cirillo

The purpose of the use cases implementation phase is to evaluate AI-SPRINT assets by using them to achieve business and technical goals specific to the use case. So the implementation strategy strongly depends on availability of AI-SPRINT assets. Since various components of AI-SPRINT will be available at different times of the project use cases need to take that aspect into account.
There are 2 points in time where evaluation results are to be reported. The first, interim, point in time is month 24 of the project. The second one, the final one, is scheduled at project end. All the use cases need to reflect that in their planning.
The key part of this deliverable is detailed planning. Every use case defines milestones required to achieve the use case goals and tasks needed to achieve them. This part also describes AI-SPRINT assets required to implement the given functionality and use case specific requirements being addressed. This detailed information can be found in section 3.
To monitor the execution of the plan use case partners will be reporting their progress on milestone level every 6 months.

Files (1.1 MB)
Name Size
D5.2 - Use case implementation plan.pdf
md5:d7848986110470ea6e604952274b190a
1.1 MB Download
  • Project deliverable

  • Open Access

22
15
views
downloads
All versions This version
Views 2222
Downloads 1515
Data volume 15.9 MB15.9 MB
Unique views 1919
Unique downloads 1414

Share

Cite as