New TopShim run:

version = topshim 2.0.0
date = 2022-05-11
time = 16:23:47.500
command = topshim 

FINE SHIMMING

Parameters:

probe = Z104275_0392
solvent = CDCl3
shim nucleus = 2H
nucleus optimised for = 13C
o1p (from lock) = 7.24 ppm

Results:


1D Shimming:
echo time must be reduced
Required SINO has not been achieved!
Please increase DURMAX if a better map quality is needed.
Required SINO has not been achieved!
Please increase DURMAX if a better map quality is needed.
Iteration  1: FWHM Before= 1.2 Hz, Target= 0.5 Hz, After= 3.2 Hz
shim changes: 
Z	+553
Z2	+1363
Z3	+1638
Z4	+15771
Z5	+12089
Z6	+15405

duration = 5 min 42 sec
completed with failure