New TopShim run:

version = topshim 2.0.0
date = 2022-03-09
time = 14:23:38.091
command = topshim 

FINE SHIMMING

Parameters:

probe = Z104275_0392
solvent = CDCl3
shim nucleus = 2H
nucleus optimised for = 1H
o1p (from lock) = 7.24 ppm

Results:


1D Shimming:
Iteration  1: FWHM Before= 0.5 Hz, Target= 0.4 Hz, After= 0.9 Hz
Iteration  2: FWHM Before= 0.9 Hz, Target= 0.3 Hz, After= 1.3 Hz
Iteration  3: FWHM Before= 1.3 Hz, Target= 0.3 Hz, After= 0.9 Hz
Iteration  4: FWHM Before= 0.9 Hz, Target= 0.5 Hz, After= 0.4 Hz
Iteration  5: FWHM Before= 0.4 Hz, Target= 0.3 Hz, After= 0.4 Hz
Iteration  6: FWHM Before= 0.4 Hz, Target= 0.3 Hz, After= 0.6 Hz
shim changes: 
Z	-391
Z2	-479
Z3	-291
Z4	-946
Z5	-5844
Z6	-15568

duration = 3 min 9 sec
completed with failure
finished Wed Mar 09 14:26:45 2022


========================================================================